Tuesday, March 30, 2010

Day 36 (29th March 2010)

They have started to paint the base coat for our house already.
Expected to be finished on Tuesday or Wednesday... Hopefully everythings goes well...
Main & Bedrooms doors are also to be arranged to install today.

Monday, March 29, 2010

Day 33 (26th March 2010)

Common Toilet
Sink and tap are all installed...
Now only left with the window...


Master Bedroom Toilet


Kitchen cabinet




Lightings are also delivered today.


Main Switch Board


Water Heater Switch and Light Switch

Thursday, March 25, 2010

Day 31 (24 March 2010)

Acrylic bi-fold door are installed today.

Day 27 (20th March 2010)

There are a few things that are put up during this time.
Toilet bowl, shower set and table top for basin are installed in both toilets.

Water Heater
Shower Set
Table Top for Basin

Air-con are also install for living room and 2 bedrooms.
Living Room

For Bedrooms

Wednesday, March 17, 2010

Day 21 (14th March 2010)

Tiles for the steps are done...



Common Toilet
All wall & floor tiles are done except for the window



Master Bedroom Toilet



Floor tiles and skirting for living room and 2 bedrooms are completed







New Rubbish Chute...

Thursday, March 11, 2010

Day 17 (10th March 2010)

The old windows are replaced...



Master Bedroom


Kitchen


Wall & floor tiles for both toilets are almost done.
Now waiting to change the window and to put in the toilet bowl, sink etc....

Common Toilet


Master Bedroom Toilet

Saturday, March 6, 2010

Day 13 (6th March 2010)

Finally the permit is approved for us to hack off the wall... :)


Common Toilet
Wall tiles are almost done...

Master Bedroom
Concealed the previous toilet entrance from the kitchen
New toilet entrance from the Master Bedroom

Day 11 (4th March 2010)

The water proofing and wall tiles for the toilet are almost done...

Common Toilet



Master Bedroom Toilet

Wednesday, March 3, 2010

Day 10 (3rd March 2010)

Time to lay the Tiles....



Hollow block was used to fill the empty space after removing the old door frame



Kitchen....

Monday, March 1, 2010

Day 5 (26 Feb 2010)

We are still waiting for the approval from HDB to hack off the wall between living room and kitchen.
Our ID did not want to waste time so while waiting for the approval, plastering was done at the kitchen and common toilet...